An efficient technique for finding the shortest non-delay schedule for a resource-constrained project

Yuval Cohen, Arik Sadeh, Ofer Zwikael

פרסום מחקרי: תוצר מחקר מכנסהרצאהביקורת עמיתים

תקציר

This paper presents a heuristic scheduling technique to solve the resource constrained project scheduling problem (RCPSP). The technique efficiently finds the best non-delay schedule (non-delay schedules are known to yield near optimal solutions). The technique is based on J stages (J being the number of activities). At each stage i, all combinations of i activities that form: (1) non-delay (2) feasible, and (3) efficient schedules, are listed. Inferior schedules are eliminated at the end of each stage. The technique is illustrated using a detailed example, and compared to other models from the literature.

שפה מקוריתאנגלית
סטטוס פרסוםפורסם - 2005
אירועIIE Annual Conference and Exposition 2005 - Atlanta, GA, ארצות הברית
משך הזמן: 14 מאי 200518 מאי 2005

כנס

כנסIIE Annual Conference and Exposition 2005
מדינה/אזורארצות הברית
עירAtlanta, GA
תקופה14/05/0518/05/05

טביעת אצבע

להלן מוצגים תחומי המחקר של הפרסום 'An efficient technique for finding the shortest non-delay schedule for a resource-constrained project'. יחד הם יוצרים טביעת אצבע ייחודית.

פורמט ציטוט ביבליוגרפי